Track record Industriebouw The idea of this track record is to show you the successive building steps of our industrial building project De Post Antwerp. A high-performance building of 50.000 m² which we have been able to finish within a term of 8 months, thanks to the skills and dedication of our project team. Track record DE POST - ANTWERP Construction of sorting hall, dispatching zone and offices |
![]() |
![]() |
Earth works: - relocation soil: 30.000 m3 - cement milling: 15.000 m3 - crushed stone bedding: 24.800 m3 Pile foundation: 4.300 pieces - precast piles beneath the structural frame - in situ grout piles beneath the floor slab |
![]() |
![]() |
Foundations works: formwork - reinforcement for pile heads |
![]() |
![]() |
Foundation works: anchor bolts for concrete structure Erection of steel structure of depot: 29.916 m2 |
![]() |
![]() |
Placing of silex concrete panels around depots: 840 m2
|
![]() |
![]() |
Placing of fire-resistant walls in Ytong and concrete: 1.730 m2 Placing of inner boxes + cladding around the depot: 6.600 m2 |
![]() |
![]() |
|
![]() |
![]() |
Placing of polyconcrete floor slab in several phases: 29.000 m2
|
![]() |
![]() |
Erection sprinkler tank. Central heating installation for radiators, ventilos and air groups. |
![]() |
![]() |
Two air groups for ventialtion offices. Ice water group for ventilos. |
![]() |
![]() |
Conditioning of each office. Conditioning chambers for IT room. |
![]() |
![]() |
8 rooftops for condtioning sorting hall.
|
![]() |
![]() |
Complete electrical installation with UPS and emergency. Complete compressed air installation for sorting. |
![]() |
![]() |
BMS (Buildinging Management System): all alarms, adjustable parameters and statuses are shown on the building management system (e.g. temperature control, HVAC, electrical installation, ...) Therefore, it enables a very functional management and maintenance of all installations. Complete fire detection system and gas extinction of IT rooms. |
![]() |
![]() |
|
![]() |
Finished building. Download PDF - Track record Woningbouw Verelst
|
||||